Iconergy partnered with Deer Trail School District 26J to deliver a high-performance new PK–12 school by providing whole-building energy modeling, CHPS support, and full lifecycle commissioning
industry
K-12
location
Deer Trail, Colorado
Solutions
Commissioning, Energy Modeling
Executive Summary
Iconergy was engaged by Deer Trail School District 26J and Cooperative Strategies to provide comprehensive CHPS consulting, energy modeling, and commissioning services for the new Deer Trail PK–12 School in Deer Trail, Colorado. The project was delivered as part of a Colorado BEST Grant and involved integrated project delivery from early design through construction and warranty. Iconergy’s work supported CHPS Verified certification, BEST grant compliance, and delivery of a high-performance, durable, and energy-efficient rural school facility.
Project Overview
The Deer Trail PK–12 School project involved construction of a new consolidated school facility to serve students across all grade levels. Iconergy supported the design team through early energy analysis and CHPS consulting to inform selection of efficient, right-sized mechanical systems and sustainable design strategies. During construction, Iconergy performed submittal reviews, site observations, functional performance testing, and testing and balancing verification to make sure systems met the Owner’s Project Requirements and CHPS criteria.
Systems Commissioned
- Variable air volume (VAV) air handling units
- Heating hot water boiler plant
- Snow melt system
- Science laboratory exhaust systems
- Domestic hot water systems
- HVAC control system
- Pumps and fans
- Low-voltage lighting controls
- Testing, adjusting, and balancing (TAB) verification
Scope of Services
- CHPS consulting and certification guidance
- Whole-building energy modeling and analysis
- Design phase commissioning and OPR/BOD development
- Submittal and design review
- Construction phase commissioning and site observations
- Functional performance testing
- Warranty phase commissioning and review
- BEST grant compliance support
Project Highlights
- New 75,000 SF PK–12 school serving a rural Colorado community
- Comprehensive CHPS consulting and verification support
- Energy modeling performed to guide system selection and meet CHPS requirements
- Full commissioning services provided from design through warranty phase
- Colorado BEST Grant–funded project
- Integrated project delivery with early involvement in Owner’s Project Requirements (OPR)
- Systems designed for durability, low maintenance, and energy efficiency
- Project completed between 2018 and 2020 with a $34 million construction budget