$1.1M EPC at an 8‑building, 388,625 SF mountain resort property, delivering mechanical, lighting, and controls upgrades that exceeded guaranteed savings by 10% in the first year.

industry

Commercial

location

Breckenridge, Colorado

Solutions

Energy & Operational Efficiency, Energy Audits, Energy Audits & Consulting, Energy Performance Contracting, Performance Assurance, Performance Contracting

Annual Savings

$73,170

Overview

A private hospitality company sought assistance to assess and upgrade energy systems at a large luxury condominium resort in Breckenridge, Colorado. Facing aging mechanical equipment and opportunities for substantial efficiency gains, the company partnered with us to perform a Technical Energy Audit and implement the resulting EPC scope. Challenges included coordinating boiler plant replacement around owner-driven construction delays and ensuring uninterrupted heating during the winter season—necessitating temporary heating solutions to maintain 24/7 building operations.

Solutions

Our team delivered a turnkey EPC solution, including a Technical Energy Audit, identification of ECMs, and full implementation of mechanical, lighting, controls, and envelope improvements. Key measures included replacement of the boiler plant serving heating and pools, BAS installation, exterior and garage lighting retrofits, and targeted insulation upgrades. We also designed and deployed temporary heating to maintain uninterrupted operations during winter construction.

Results

The project outperformed its guaranteed savings, achieving a 10% improvement and generating $73,170 in verified first‑year savings. The upgrades improved energy performance, enhanced guest comfort, modernized building systems, and reduced operational risks. The EPC established a foundation for future phases of energy improvements and operational optimization across the resort campus.

Project Highlights

  • $1.1M EPC project across 8 buildings (388,625 SF)
  • Exceeded guaranteed savings by ~10% ($73,170 first-year savings)
  • Comprehensive boiler plant replacement (building heat, pool, and hot tub boilers)
  • Exterior & parking garage lighting retrofits
  • New BAS installation and insulation improvements
  • Seamless implementation despite heating‑season scheduling constraints

Energy Conservation
Measures

  • Exterior lighting retrofits
  • Parking garage lighting retrofits
  • Boiler plant replacement (heating, pool, hot tub)
  • Building automation system (BAS) installation
  • Insulation improvements

Related Projects

Row midpoint Shape Decorative svg added to bottom

Let’s Build Together

CEG Solutions helps public and private clients modernize infrastructure, achieve deep savings, and enhance energy and operational efficiency — without disrupting mission-critical operations. Let’s talk about what we can achieve together.

Or call us 703-294-5600

"*" indicates required fields

This field is for validation purposes and should be left unchanged.