Boulder, Colorado

Boulder Valley School District

Iconergy partnered with Boulder Valley School District to improve comfort, efficiency, and system performance across multiple schools through district-wide retro-commissioning.

industry

K-12

location

Boulder, Colorado

Solutions

Commissioning, Retro-Commissioning

Executive Summary

Iconergy has provided long-term energy efficiency, commissioning, and retro-commissioning services for Boulder Valley School District (BVSD) as part of the District’s 2014 Bond Program and subsequent post-bond initiatives. Services have been delivered across more than 20 schools and district facilities, supporting HVAC upgrades, system optimization, sustainability goals, and improved indoor environmental quality. This ongoing partnership spans over a decade and more than one million square feet of K–12 facilities.

Program Overview

As part of BVSD’s Bond Initiatives, Iconergy supported the portion of the bond dedicated to HVAC upgrades and energy efficiency improvements. The program included schools receiving capital upgrades, as well as facilities not receiving major construction but benefiting from retro-commissioning of existing high-efficiency mechanical systems.

Scope of Services

• ASHRAE Level energy audits
• Retro-commissioning of existing HVAC and control systems
• Commissioning of new and retrofit HVAC systems
• Building automation system (BAS) sequence review and verification
• Testing, adjusting, and balancing (TAB) verification
• Sustainability consulting and greenhouse gas reduction support
• Energy modeling for new construction and modernization projects
• Measurement and verification (M&V) services

Representative Facilities Served

• Arapahoe Campus
• Boulder Community School of Integrated Studies
• Centennial Middle School
• Columbine Elementary School
• Community Montessori
• Escuela Bilingüe Pioneer
• Fireside Elementary School
• Foothill Elementary School
• Heatherwood Elementary
• Horizons K-8 School
• Kohl Elementary School
• Lafayette Elementary School
• Manhattan Middle School
• Mapleton ECE School
• Monarch Schools Underground Piping
• Nederland Bus Building
• Nederland Elementary School
• Nederland Middle School
• New Vista High School
• Platt Middle School
• Ryan Elementary School

Project Highlights

  • District-wide commissioning and retro-commissioning program across 20+ K–12 facilities
  • Over 1,000,000 square feet of school and support facilities evaluated and optimized
  • Support of BVSD’s 2014 Bond Program focused on HVAC upgrades and system improvements
  • ASHRAE energy audits and retro-commissioning performed at each participating school
  • Commissioning and verification of HVAC retrofit systems, including added air conditioning
  • Full commissioning scope including HVAC equipment, BAS, and TAB verification
  • Ongoing sustainability consulting, energy modeling, and measurement & verification services
  • Support of district greenhouse gas reduction, indoor air quality, and sustainability goals
  • Construction value of approximately $1 million implemented over an 8-year period
  • Services initiated in 2014 and continuing through ongoing on-call engagements

Related Projects

Row midpoint Shape Decorative svg added to bottom

Let’s Build Together

CEG Solutions helps public and private clients modernize infrastructure, achieve deep savings, and enhance energy and operational efficiency — without disrupting mission-critical operations. Let’s talk about what we can achieve together.

Or call us 703-294-5600

"*" indicates required fields

This field is for validation purposes and should be left unchanged.